5 Churchill Place – Canary wharf

Radiological Resin Processing Plant
November 28, 2016
Show all

5 Churchill Place – Canary wharf

Location

5 Churchill Place - Canary wharf

Requirement

To design, install, commission 2 gas suppression systems in 2 data comms rooms within 6 weeks, enquiry was received on the 5th December 2016.

Solution

Decision was made to go with a IG55 suppression system for both rooms, both IG55 systems was designed, installed, commissioned and was handed over on the 30th of December 2016, 25 days from enquiry to handover (including the Christmas break)

Benefit

Customer was able to move into their office on time and no penalty clauses was incurred by the main contractor.